Administration wanted to share the street milling dates from our Engineering Department…
Mayor Henderson
Milling dates:
Thurs and Fri. Sep. 14 and 15 – Cemetery Rd. and Bellefontaine St.
Mon. Sept. 18 – Rosewood/Woodlawn Dr. and Daisy Dr.
Tues. Sept. 19 – Daisy Dr. and Canterbury
Wed. Sept. 20 – Seltzer St. and Park St.
Thurs. Sept. 21 – Main St. and Springwood Ln.
Cement Stabilization dates:
Wed. and Thurs. Sept. 20 and 21 – Rosewood/Woodlawn, Daisy, and Canterbury.
Paving Dates:
Wed. and Thurs. Sept. 20 and 21 – Cemetery Rd. and Bellefontaine St.
Fri. Sept. 22 – Seltzer St. and Park St.
Mon. Sept. 25 – Rosewood/Woodlawn and possibly Daisy.
Tues. Sept. 26 – Daisy Dr. and Canterbury.
Wed. Sept. 27 – Main St. and Springwood Ln.